Date of manufacture:
28.10.2017
Product:
ICE cooling unit CAT 3516

Challenge

"VT ENERGY" Ltd acquired cooling radiators from Belarusian supplier who does not manufacture products under customer needs . The problem was that the supplier was not able to provide a radiator of non-standard size in a short time.

Solution

NZTO has designed and manufactured universal cooling unit in 25 days.

PJSC "Kombinat Magnesite »

Date of manufacture:
24.09.2017
Product:
COOLERS FOR SHAFT FURNACES

Challenge

The necessary product was withdrawn. Logistics at the enterprise is hampered by harsh climatic conditions and is made up for several times a year. It was necessary to deliver and urgently install the radiator within three weeks, otherwise, the company suffered huge losses due to idle equipment.

Solution

NZTO has designed and manufactured cooling radiator in two weeks. Thereby significantly saved LLC “Magnezit” funds.

PJSC "Kombinat Magnesite »

Date of manufacture:
26.11.2017
Product:
ICE cooling radiator CAT R 1600

Challenge

Due to the manufacturing technology and operations in the mine, all-welded radiator core was very quickly contaminated and cemented, which led to the unsuitability of the radiator and its frequent replacement.

Solution

Thanks to NZTO technology of manufacturing radiators with replaceable tubes, air passage between the cooling tubes was expanded, thus avoiding radiator to be overheated. And work longer.